Seven Points of Adjustment and Installation of Drum-Type Chicken Manure Dryer

 Chicken manure dryer is the main equipment for the harmless and resource recovery of chicken farms (including broiler, layer, breeder breeding sites), and it is one of the technological links of processing organic fertilizer equipment. The chicken manure tumble dryer is the same as other industrial dryers, which are all cylinders, as short as a few meters, often 20 to 30 meters. Matters needing attention in the process of adjusting and installing equipment affect its efficiency and noise control.

There are seven main points for attention during the installation and adjustment of the chicken manure dryer:

1. Draw the base line: Make the cross line, the elevation line, and the center mark on the base target plate to achieve convenient and accurate embedding, and consider that the base will not be covered after installation.

2. Install the base and the tug: level the position of the shim, draw the center line of the base and the tug, according to the requirements of the drawing, find the installation position of the base and the tug, level and lay it, first grouting the foundation hole when the concrete reaches a certain strength , Tighten the anchor bolts, and then install the tumble drying machine cylinder after passing the review.

3. Installation simplified and rolling enclosure: first install the rolling enclosure on the cylinder, the concave joints needed for fixing should be arranged in a positive and negative staggered configuration, and adjust the thickness of the shim to keep the contact between the rolling ring and the concave joint corresponding Do not match the gap between the two, and spot weld the head of the concave joint bolt with the cylinder.

4. Install the big gear: Before installation, check that there should be no collision marks on the interface of the mating surface, clean the contact surface of the big gear and the cylinder, and then carefully align the two gear halves and tighten the interface bolts to install the big gear on the cylinder. superior. Rotate the cylinder to check the radial run-out and lateral swing of the big gear until the calibration is qualified.

5. Install the pinion gear, reducer, and motor: According to the large gear that has been installed, adjust the meshing parameters of the large and small gears and meet the requirements of the equipment. Fix the position of the pinion and reducer motor.

6. Install the gear cover: make it symmetrical with the edge of the gear.

7. After the six adjustments, a second grouting is required. The installation review and debugging work related to grouting are carried out simultaneously to ensure the installation quality of the organic fertilizer equipment and chicken manure dryer.



Strictly complying with the above seven-step adjustment items can effectively extend the service life of the chicken manure drying machine, improve the efficiency of use, and reduce the failure rate of the dryer. Therefore, strictly refer to the manufacturer's assembly drawings and basic drawings, assembling and debugging requirements for standard construction, which is an effective measure for the adjustment and installation of the chicken manure tumble dryer. There are many other detailed requirements, which are generally required and emphasized in the parameters and instructions.